Estimating

How Much Concrete Do I Need? Formulas, Examples, and a Free Calculator

The core cubic-yard formula, worked examples for slabs, footings, and piers β€” plus a quick-reference table you can screenshot for the truck.

C
0.333 ft
four inches, in feet

Whether you're pricing a 20Γ—20 garage slab or pouring footings for a deck, the first question is always the same: how many cubic yards do I need to order?

Get it wrong and you're either paying short-load fees for an emergency half-yard, or watching the truck driver dump your leftover concrete in a pile you didn't budget for. Neither is a good look in front of a customer.

This guide covers the core formula, worked examples for the most common pour types, waste factor rules of thumb, and a quick-reference table you can screenshot for the truck.

The Core Formula

Every concrete volume calculation comes back to the same equation:

Cubic Yards = (Length Γ— Width Γ— Thickness) Γ· 27

All measurements in feet. Convert inches to feet by dividing by 12.
4 inches = 0.333 ft  |  5 inches = 0.417 ft  |  6 inches = 0.5 ft

That's it. Length times width gives you square footage. Multiply by thickness (in feet) and you get cubic feet. Divide by 27 because there are 27 cubic feet in one cubic yard.

The tricky part isn't the math β€” it's knowing what to plug in, how much waste to add, and how to handle shapes that aren't perfect rectangles.

Common Slab Calculations

Standard Driveway (20 Γ— 20 at 4 inches)

Example: 2-car driveway
Length: 20 ft  |  Width: 20 ft  |  Thickness: 4 in (0.333 ft)

20 Γ— 20 Γ— 0.333133.2 cubic feet
133.2 Γ· 274.94 cubic yards
Add 10% waste: 4.94 Γ— 1.105.43 CY
β†’ Order5.5 cubic yards

Garage Floor (24 Γ— 30 at 4 inches)

Example: standard 2-car garage
Length: 24 ft  |  Width: 30 ft  |  Thickness: 4 in (0.333 ft)

24 Γ— 30 Γ— 0.333239.76 cubic feet
239.76 Γ· 278.89 cubic yards
Add 10% waste: 8.89 Γ— 1.109.78 CY
β†’ Order10 cubic yards

Sidewalk (4 Γ— 50 at 4 inches)

Example: 50-foot walkway
Length: 50 ft  |  Width: 4 ft  |  Thickness: 4 in (0.333 ft)

50 Γ— 4 Γ— 0.33366.6 cubic feet
66.6 Γ· 272.47 cubic yards
Add 10% waste: 2.47 Γ— 1.102.72 CY
β†’ Order3 cubic yards
Contractor tip: Always round up to the nearest half yard when ordering ready-mix. Coming up short mid-pour is the most expensive mistake you can make β€” you'll pay a short-load fee for the second truck, plus your crew is standing around waiting. An extra quarter-yard costs $40. A cold joint costs you the job.

Footings and Walls

Footings and walls use the same core formula, but you're usually working with depth instead of thickness, and the dimensions are less forgiving because structural requirements are fixed.

Continuous Footing (12 in wide Γ— 12 in deep Γ— 60 ft long)

Example: garage perimeter footing
Length: 60 ft  |  Width: 1 ft (12 in)  |  Depth: 1 ft (12 in)

60 Γ— 1 Γ— 160 cubic feet
60 Γ· 272.22 cubic yards
Add 15% waste (footings have irregular edges): 2.22 Γ— 1.152.55 CY
β†’ Order3 cubic yards

Pier Footings (Round, 12 in diameter Γ— 36 in deep)

Volume = Ο€ Γ— (radiusΒ²) Γ— depth

For a 12" diameter pier: Ο€ Γ— (0.5Β²) Γ— 3 = 2.36 cubic feet per pier
2.36 Γ· 27 = 0.087 CY per pier
For a deck with 8 piers: 0.087 Γ— 8 = 0.70 CY. Add 20% waste for round forms (concrete doesn't cooperate with Sonotubes as nicely as you'd like) and you're at about 0.84 CY β€” order 1 yard.

Contractor tip: Use a higher waste factor for footings (15%) and pier footings (20%) than for flatwork (10%). The subgrade is never perfectly flat, and the forms bow more than you expect. The extra half-yard is insurance, not waste.

Quick Reference Table

Here's a table you can screenshot and keep on your phone. It shows cubic yards needed for common slab sizes at 4-inch thickness, before waste factor.

Slab Size Sq Ft CY (4 in) CY (5 in) CY (6 in)
10 Γ— 101001.231.541.85
12 Γ— 121441.782.222.67
16 Γ— 162563.163.954.74
20 Γ— 204004.946.177.41
24 Γ— 245767.118.8910.67
24 Γ— 307208.8911.1113.33
30 Γ— 3090011.1113.8916.67
30 Γ— 40120014.8118.5222.22
40 Γ— 60240029.6337.0444.44

Remember: add 10% for waste on clean flatwork, 15% for footings, and 20% for pier footings or complex shapes.

What About Irregular Shapes?

Not every pour is a rectangle. Curved driveways, L-shaped patios, and angled walkways are common. For these, you have a few options:

The Waste Factor: How Much Extra to Order

The waste factor is the gap between the math and reality. Your subgrade isn't laser-flat. Your forms bow out slightly under pressure. The truck driver spills a little during the pour. The finishers pull a little more than expected on the edges.

Here's what experienced contractors typically add:

Pour Type Waste Factor Why
Clean flatwork (slab, driveway)10%Minor subgrade variation, form movement
Footings15%Irregular trench walls, wider bottom than planned
Pier footings (Sonotubes)20%Ground water, tube expansion, overpouring tops
Steps and complex forms15–20%Multiple pours, tight forms, more spillage
Pump poursAdd 0.25–0.5 CYConcrete stays in the line β€” it doesn't all reach the slab
The golden rule: It's always cheaper to have a little extra concrete on site than to order a short-load second truck. A typical short-load fee is $50–$150 per yard under the minimum, plus your crew is standing around burning daylight. The extra half-yard might cost you $80 β€” use it for a small pad, a set of stepping stones, or fill a form you've been putting off. That's a lot cheaper than a cold joint.

What About Cost?

Ready-mix pricing changes constantly and varies by region, PSI rating, delivery distance, and order size. Rather than listing numbers that'll be outdated in six months, here's what to know: always call your local batch plant for a current per-yard quote, ask about their short-load minimum (usually 8–10 CY β€” ordering less means a surcharge), and check if Saturday or early-morning delivery costs extra. Get quotes from at least two suppliers.

For small jobs under 1–2 cubic yards, price out bagged concrete too. An 80-pound bag of Quikrete yields about 0.6 cubic feet, so one cubic yard takes roughly 45 bags. Depending on your local ready-mix minimums and short-load fees, bags can be comparable or cheaper on small pours β€” and you don't have to wait for a truck.

Common Mistakes That Cost You Money

Skip the Math β€” Use a Free Calculator

If you're doing this calculation multiple times a week across different jobs, there's no reason to do it by hand every time. Our free concrete calculator handles all of this β€” rectangular slabs, curves, footings, walls, and irregular shapes β€” with automatic waste factor and cubic yard totals.

No account needed. Just punch in your dimensions and get the answer.

Open Free Calculator β†’
C

ConCal Team

Estimating guides and field references from the team behind ConCal β€” the free drawing-based concrete calculator contractors use to take off slabs, footings, and curbs in minutes. Try the free calculator.

Share X / Twitter Facebook LinkedIn